A national brand needed to increase distribution quickly.
When this internationally known brand needed to increase its bottling and distribution capacity quickly, Haskell was engaged to help guide the mammoth effort. After a multi-site search for a new manufacturing facility, Haskell was awarded the next-generation bottling facility which, upon completion, was the world’s largest LEED® 2.1 Gold food and beverage facility.
We set several key benchmarks in completing the massive project.
The new bottling and distribution facility included 24,000 square feet of offices, 250,000 square feet of process and packaging space and a 656,000-square-foot warehouse. Also included in the slab-on-grade project was an on-site rail shed, guardhouse and wastewater treatment plant.
The team powered beyond challenges to deliver on a grand scale.
The project overcame substantial challenges, including poor soil conditions, adverse winter conditions, changing business requirements, process and packing requirements, and many others, which were all resolved quickly and professionally. The breakthrough project earned accolades, including the ABC Award of Merit, a Tilt-Up Concrete Association Achievement Award and LEED Gold Certification.
Sustainability by Design
- LEED Gold Certified – 44 points. World’s largest LEED Gold Certified food & beverage facility at time of construction.
- Energy Conservation – HVAC and lighting perform 48 percent better than the baseline ASHRAE standard.
- Natural Spaces – Preserved more than 50 percent of original site as naturalized open space.
- Water Conservation – Reduced potable water use by 72 percent.
- Wastewater Recycling – Methane gas from on-site wastewater treatment system captured and used for boiler fuel.
- Renewable Energy Credits – Purchased equivalent to 100 percent of the building’s energy consumption.
- Green Education Program – Sun-tracking photovoltaic array, permanent site and building signage, posters and brochures.
- Materials – 15 percent of building materials came from recycled sources, while 40 percent were produced regionally (10 percent produced locally). Diverted 80 percent of construction waste from landfills.
Related Topics
Talk to a Subject Matter Expert
Project Highlights
942,034 SF total
Fastest hot fill production lines in the world
Delivery Method: Design-Build
Related Projects
Northlake, Texas
Farmer Brothers EPC Coffee Manufacturing
Confidential Location
Confidential Beverage Client Manufacturing Plant
Monterrey, Nuevo Leon, Mexico
PepsiCo Bakery Innovation Center
Related News & Insights
The Real Cost of Moving from Artificial to Natural Flavors and Colors
Regulatory scrutiny and consumer expectations make economic planning essential, not optional. Learn how to build a long-term reformulation roadmap.
Fabrication, Sales and Service Underpin for Eric Jensen’s Leadership
Learn how the Haskell Superintendent's technical depth and people skills make him 'the glue that keeps it all together' on complex projects.
Haskell Partners with NEFBA to Expand Construction Trade Education
Learn NEFBA's vision for a state-of-the-art home for the next generation of skilled labor. See how Haskell invests in the future construction workforce.
The Fizz Factor: Learn Why CO2 Is Critical in Beverage Processing
Discover the science behind carbonated beverages and how Haskell SME Dwight Garrels helps clients optimize critical components of manufacturing.