COJ LaSalle Street Drainage Improvements

Jacksonville, Florida

The City of Jacksonville needed a long-term solution to flooding in the San Marco neighborhood.

Given LaSalle Street’s proximity to the St. Johns River, homes and businesses experienced persistent flooding for decades. The City of Jacksonville selected Haskell and design partner AECOM to design, permit and construct a $43.3 million stormwater pump station and collection system within the 149-acre LaSalle Street Basin.

The new system is designed to reduce frequent flooding.

The pump station includes two stormwater treatment units, a wet well, five submersible pumps and emergency generator for standby power. A 24-inch discharge system connects the pumps to a 48-inch force main that discharge into the St. Johns River, even at elevated river levels. The project also includes replacement of gravity stormwater piping, drainage inlets, a replacement river bulkhead, electrical distribution, pump controls, instrumentation and SCADA integration.

Groundwater conditions required a new excavation approach.

Before work could begin, the team had to address existing groundwater conditions. Because groundwater was two to three feet below the surface, Haskell needed to develop a solution to safely dig another 35-38 feet below. Original plans to install secant piles, capable of groundwater cutoff to 32 feet below sea level, were only able to lower the groundwater level 14 feet. The design-build team reworked plans to propose a wet dig instead, which allowed for deeper excavation and installation of an underwater slab while maintaining the original schedule. Teams were then able to pump the water out to create stable conditions for construction.

Community outreach helped manage construction in an active neighborhood.

The second phase extended across more than 100 acres and required work near homes, businesses, roads and utilities. The project team divided construction into manageable segments and restored access before advancing to new areas when possible. Town halls, open houses, door-to-door updates and printed notices kept residents informed about road closures, property access and upcoming work.

The project helps alleviate San Marco’s flooding risk.

The completed system is designed to withstand severe wet weather events, maintaining flood elevations below existing building floors. The pump station and collection system will move stormwater more efficiently through the LaSalle Street Basin and into the St. Johns River.

Talk to a Subject Matter Expert

Joe Kantor

Division Leader, Water – East Region

contact Joe

Project Highlights

$43.3 million progressive design-build project

149-acre drainage basin

Five submersible stormwater pumps

Two stormwater treatment units

River bulkhead replacement

Roadway, paving and site improvements