HP Hood: Packaging Line Replacement

One coordinated system in an active dairy facility in Winchester, Virginia.

Haskell delivered the EPC/design-build replacement of the legacy filler and packaging line with a new aseptic filler and integrated packaging system at HP Hood’s Winchester, Virginia, facility. Working within 13,800 square feet in the center of an operating dairy plant, the team relocated equipment originally purchased for another facility, upgraded the room and utilities and coordinated modifications across neighboring lines. A point-cloud scan and comprehensive 3D model reduced clashes and field rework, while phased installation and four independent startup efforts protected ongoing production.

System at a Glance

13,800

square feet

130

96-oz bottles per minute (BPM)

10

months FROM design start to saleable product

3

weeks ahead of target

Client Challenge

  • Relocate and integrate equipment originally purchased for another facility.
  • Fit fixed equipment into limited floor space and existing infrastructure.
  • Modify multiple production lines while minimizing downtime in an operating plant.
  • Adapt commissioning activities to product demand and plant priorities.
  • Execute the project within an active operating facility without disrupting operations or compromising product safety.

Haskell Solution

  • Captured existing conditions with point-cloud scanning and a coordinated 3D model.
  • Used a phased installation strategy with four independent startup efforts.
  • Integrated packaging equipment, controls, utilities and facility modifications.
  • Provided 24-hour startup support, OEM training, spare-parts planning and turnover resources.
  • Implemented dust-containment measures (negative-pressure,
    temp-walls), controlled access between construction and plant areas and maintained close coordination with Plant Operations.

integrated Design-build Value

Haskell coordinated filler relocation, packaging integration, controls, utilities, facility modifications and four phased startups under one team – protecting active production while achieving first product three weeks ahead of the contractual target.

Process interfaces, packaging, controls and facility systems integrated as one operating platform

Filler and sanitary piping equipment at HP Hood's Winchester, Virginia dairy facility.
Packaging line and palletizing conveyors at HP Hood's Winchester, Virginia dairy facility.

Simplified Product Flow

Receiving

Process

Filler

Packaging

Palletizing

ASRS

Outbound
Haskell Scope of Work

Process + Utilities

Product piping, UV and chemical skids; new steam skid, water loop, compressed air, lighting and power.

Facility Modifications

Slab and underground plumbing work, raised IMP ceiling, panel platform, resinous and dairy brick flooring.

Controls + Data

Haskell integrated the packaging line controls into a coordinated PLC/HMI platform that unified OEM interfaces, accumulation logic, fault recovery, inspection, reject tracking and operator visibility — turning multiple pieces of equipment into one integrated operating system.

Packaging Integration

Haskell engineered the line as an integrated system, coordinating equipment interfaces, accumulation, fault recovery, inspection, reject tracking and controls across multiple OEM packages. The system included the overcapper, labeler, inspection, bottle turner, laner, case packer, palletizer and conveyors for two 96-ounce SKUs at 130 BPM.

Quality + Traceability

Leak, cap, label, date-code and open-case inspection with case-code verification and reject tracking.

Operational Readiness

24-hour technical support, OEM training, spare-parts recommendations and organized maintenance documentation.

Commissioning Strategy

Packaging-line checkout, water runs and non-salable-product testing were aligned with filler startup. Haskell provided 24/7 on-site support for the first two weeks of operation and progressed through 1-hour, 8-hour and three consecutive 8-hour performance tests before handoff.

Performance-test boundary
Site Acceptance Test (SAT) measured performance from filler discharge through palletizer; upstream bottle supply and downstream pallet-conveying disruptions were excluded.

Key Milestones

Mechanical
Completion

Day 0

4/16

First
Water

Day +5

4/21

First
Product

Day +12

4/28

Saleable
Product

Day +26

5/12

Pass

96.92%

1-hour OEE
Target 90%

Pass

88.38%

8-hour OEE
Target 85%

Pass

84.54% AVG

Three 8-hour shifts
Target 80% each

Three-shift results: 80.91%, 89.50% and 83.20%

Verified Startup Performance

Target
Actual
Critical Mechanical checkouts
Completion prior to FIRST production
100%
100%
Electrical checkouts
Completion prior to first production
100%
100%
Functional tests
Completion prior to first production
100%
100%
recordable incidents during commissioning
0
0

Strongest proof point

Haskell delivered first production three weeks ahead of the contractual target, within budget and with zero recordable incidents, while maintaining hygienic separation and protecting ongoing plant operations.

Business Impact

The replacement provided a faster, more maintainable 96-oz. packaging platform designed to improve reliability, simplify maintenance and support more consistent production.

Haskell delivers over $3 billion annually in Architecture, Engineering, Construction (AEC) and Consulting solutions to assure certainty of outcome for complex capital projects worldwide. Haskell is a global, fully integrated, single-source design-build and EPC firm with 3,000 highly specialized, in-house design, construction and administrative professionals across industrial and commercial markets. With 25+ office locations around the globe, Haskell is a trusted partner to global and emerging clients.

Related News & Insights