Five Factors Are Vital to Delivering Operationally Ready Data Centers
Learn from Haskell's Moises Corral how project controls can track the dependencies that move systems from construction to testing and turnover.
What makes data center construction different from other building types? It starts with one requirement: A data center must protect critical loads when equipment fails, systems interact unexpectedly or maintenance takes part of the infrastructure offline. That requirement changes how the facility is designed, built, commissioned and transferred to operations.
Data center delivery brings electrical, mechanical, controls, fire protection, communications and architectural systems together as interconnected infrastructure. A seemingly minor deviation in one system can affect several others, and an installation deficiency may remain hidden until systems are tested together.
Physical completion is only one milestone. The larger objective is to demonstrate that the infrastructure can perform under normal operation, abnormal conditions and defined failure scenarios.
Five closely related factors shape that work: fault tolerance, continuity, redundancy, speed and integration.
Fault Tolerance: Planning for Failure
Data center design cannot assume that every component will operate continuously.
Equipment fails. Components require maintenance. Utility power can be interrupted. Controls can produce unexpected responses. Environmental conditions can move outside their intended ranges.
Mission-critical infrastructure has to respond to defined failure scenarios while protecting critical loads. Depending on project requirements, that strategy may involve fault tolerance, failover capabilities, concurrent maintainability or redundant capacity.
Redundancy shown in a design does not prove that a facility will respond as intended. That response must be verified through testing.
Commissioning provides a structured process for evaluating equipment and system performance. Functional testing confirms how individual systems operate. Integrated testing evaluates how the infrastructure responds when systems interact during abnormal conditions, failures and recovery.
Failure can’t always be eliminated, but it can be anticipated, contained and tested.
Continuity: Moving From Completion to Readiness
Between construction completion and operational readiness lies a period of verification when teams must confirm that components work individually, systems perform as intended and the integrated infrastructure can support required operating scenarios.
Commissioning should begin well before final testing. Incorporating it during design and carrying it through construction, testing and turnover helps identify unclear requirements, coordination gaps and system interface risks before they affect operations.
Continuity depends on evidence that the infrastructure can maintain required functions under the conditions it was designed to withstand.
Redundancy: Evaluating the Entire System
Redundancy is often reduced to a designation such as N+1. The designation matters, but it does not tell the whole story.
Teams need to evaluate redundancy across the architecture, including power generation, electrical distribution, uninterruptible power supply systems, switchgear, cooling equipment, controls, fire protection and communications. They must also examine the dependencies among those systems.
A facility can have redundant components and still face a single point of failure. Two pieces of equipment may depend on the same control platform, power source, physical route or operating sequence. Losing that shared dependency could make both components unavailable.
The more useful question is what happens to operations when one component becomes unavailable. Designed redundancy becomes operational resilience only after the intended response has been demonstrated.
Speed: Accelerating Delivery Without Losing Control
The American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) notes that growing demand for computing capacity is compressing schedules for data center design, procurement, construction and commissioning.
Faster delivery requires teams to manage more frequent interactions among disciplines. Design changes affect procurement. Vendor information influences installation. Field conditions shape commissioning. Operational requirements affect testing and turnover. Each decision can alter the critical path.
Projects may respond through partial system turnover, earlier commissioning involvement, block-by-block testing, progressive turnover, interface management, look-ahead planning and readiness tracking. These approaches allow some activities to proceed concurrently, but they also increase the need for disciplined coordination and clear acceptance criteria.
From a project controls perspective, completed installation activities do not necessarily mean a system is ready for testing. Its prerequisites, controls logic, vendor support and connected systems must also be ready.
Tracking those dependencies provides a more reliable view of whether each system can advance to the next stage.
Integration: Testing the System of Systems
Individual systems can pass their tests while the facility still fails to perform as designed.
A chiller, pump, generator, uninterruptible power supply and control platform may each operate correctly in isolation. The weakness may emerge only at an interface: between electrical and mechanical systems, HVAC equipment and controls, fire alarms and emergency power or design intent and field operation.
Integrated systems testing evaluates those relationships by examining how the full infrastructure responds to defined scenarios, including equipment failures, power transitions and recovery sequences.
The goal is to prove the systems work together, not just individually.
Proving Operational Readiness
Fault tolerance, continuity, redundancy, speed and integration converge in one requirement: The delivery team must demonstrate that the infrastructure is ready to support critical operations.
That demonstration should answer four questions:
- Does the infrastructure perform as designed?
- Does it protect critical loads during defined component failures?
- Do connected systems respond correctly under normal and abnormal conditions?
- Can a team prove that performance before operations are placed at risk?
That is what makes data center construction different. The work is complete only when the integrated infrastructure has demonstrated that it can perform under the conditions it was designed to manage.
About the Author: Moises Corral is a Haskell Project Controls Analyst with more than 20 years of experience supporting complex capital projects in the energy and data center sectors. His experience includes Primavera P6, earned value management, critical path analysis and Power BI. He supports Haskell’s fast-track data center programs by connecting schedule, cost, risk and field information to help project leaders make informed decisions.
Related News & Insights
TechWeek Message: Early Integration is Key to Outcomes and Quality
Explore how data centers and modular projects each demand the same discipline: resolve critical details early and carry quality through every phase.
Grace Foster-Reid Leads With Purpose Through Every Storm
Learn how the Jamaican Project Manager earned Haskell's Living the Values Award for her leadership, compassion and commitment to others.
With Contribution from Haskell, Last Energy Completes its Series C
Learn what is next for this young company that is on the forefront of new nuclear deployment and pushing toward a clean-energy future.
Haskell to Push Modular Energy Integration in Wells Fargo Incubator
Learn how Haskell and seven other cohort members will leverage expert support to advance adoption strategies for cutting-edge energy solutions.